Floating LNG Projects in Indonesia: Navigating Offshore Approvals, Gas Utilisation and Project Contract Structures
Floating liquefied natural gas projects can offer a way to monetise offshore gas where a conventional onshore liquefaction facility may be difficult to develop. In Indonesia, however, an…

Floating liquefied natural gas projects can offer a way to monetise offshore gas where a conventional onshore liquefaction facility may be difficult to develop. In Indonesia, however, an offshore location does not create a single, self-contained licensing route. The approvals depend on how the project is structured: as part of upstream production under a production sharing contract, as a separate downstream gas-processing business, or through a combination of the two.
The principal framework includes Law No. 22 of 2001 concerning Oil and Natural Gas, as amended by Law No. 6 of 2023 concerning the Enactment of Government Regulation in Lieu of Law No. 2 of 2022 on Job Creation (Oil and Gas Law); Government Regulation No. 35 of 2004 concerning Upstream Oil and Gas Business Activities, as amended by Government Regulations No. 34 of 2005 and No. 55 of 2009; and Government Regulation No. 28 of 2025 concerning the Implementation of Risk-Based Business Licensing (GR 28/2025). For downstream energy and mineral resources activities, Minister of Energy and Mineral Resources Regulation No. 7 of 2026 establishes the current business activity standards under the risk-based licensing framework (MEMR Regulation 7/2026).
1. The Project Structure Determines the Licensing Route
“Floating LNG” describes a project configuration, not a single Indonesian business licence. A floating facility may be a floating liquefaction vessel connected to an offshore gas field, a floating storage and regasification unit, or infrastructure owned or operated by a third party under a tolling or service arrangement. These structures may engage different sets of approvals.
Where liquefaction forms part of an upstream field development, the project will generally need to be assessed under the applicable production sharing contract (PSC), the approved development plan, and the upstream oversight framework administered by the Special Task Force for Upstream Oil and Gas Business Activities (Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi or SKK Migas). Government Regulation No. 35 of 2004, as amended, remains part of the upstream framework.
A separately operated facility that processes gas for a fee, purchases and processes gas, stores LNG, transports gas, or trades LNG may also fall within downstream licensing requirements. GR 28/2025 and MEMR Regulation 7/2026 now provide the current risk-based licensing framework and technical standards for relevant downstream activities, including gas processing and LNG trading. The standards address matters such as the business plan, supply and customer arrangements, facilities, location and technical readiness.
The distinction is consequential. GR 28/2025 describes downstream gas processing as an activity that includes liquefaction, while excluding field processing. Whether a particular floating liquefaction facility constitutes excluded field processing, a separately licensed downstream facility, or an integrated arrangement requires project-specific analysis. The facility’s technical role, ownership, location, contractual allocation of responsibilities and relationship to the upstream field should be reviewed with the relevant authorities before the project company settles its licensing plan.
2. Upstream Approvals: PSC, Development Plan and SKK Migas Oversight
For an upstream-integrated FLNG project, the PSC is the starting point for determining the contractor’s rights and obligations. The PSC does not, by itself, remove the need for project approvals or other statutory permits. Sponsors should establish which party is responsible for the floating facility and whether the facility is included in the approved field development plan and related work programmes and budgets.
The development plan must address how the gas will be produced and monetised, including the technical and commercial case for liquefaction, the relationship between the offshore facilities and the reservoir, and the proposed route to market. Any material changes to the development concept, including changes to processing capacity, field configuration or export arrangements, should be assessed against the existing approvals and PSC governance requirements.
SKK Migas’s role is particularly relevant to procurement, contracting and project oversight. The upstream contractor should confirm how the development, engineering, procurement, construction, installation and commissioning arrangements fit within the approved plan and the applicable upstream procurement procedures. A private contract with a shipowner, engineering contractor or LNG buyer cannot substitute for an upstream approval where one is required.
The Oil and Gas Law and its implementing framework also place upstream production within a state-supervised regime. Sponsors should therefore clarify the project’s ownership and control structure, the treatment of assets and operating responsibilities under the PSC, and the route by which costs, production volumes and LNG sales are recognised within the upstream arrangement.
3. Downstream Business Licensing for Processing, Storage and LNG Trading
Where a project company conducts a separate downstream activity, it should identify the relevant business activities and licences under GR 28/2025 and MEMR Regulation 7/2026. These may include gas processing, gas transportation, gas storage and LNG trading, depending on the actual functions performed by the company.
MEMR Regulation 7/2026 requires project-specific information for downstream licensing. For gas processing, the standards address the gas supply, product specifications, production and marketing plans, consumers, facilities and locations. They also require applicable spatial approvals for the facilities. For LNG trading, the standards call for information on supply sources, prospective customers, commodity specifications, locations, facilities and the proposed business scheme.
An upstream PSC contractor should not assume that its upstream status automatically authorises an affiliated company to conduct downstream processing or trading. Conversely, an LNG tolling company should not assume that its downstream business licence gives it rights to produce or take custody of upstream gas. The licensing analysis should map each entity to its actual activity and contractual role.
The current risk-based licensing framework is implemented through the Online Single Submission (OSS) system. Government Regulation No. 28 of 2025 and Minister of Investment and Downstreaming/Head of the Investment Coordinating Board Regulation No. 5 of 2025 establish the relevant business licensing procedures. The entity’s business identification number and activity classifications should match the approvals being sought and the actual operations to be performed.
4. Marine Spatial Conformity and Offshore Site Approvals
A floating unit, its mooring system, subsea connections, offshore pipelines, exclusion or safety zones, and any associated marine infrastructure may each have spatial implications. A project should therefore assess whether its planned marine-space use requires a Marine Spatial Utilisation Conformity approval or confirmation (Kesesuaian Kegiatan Pemanfaatan Ruang Laut or KKPRL), and which authority is responsible for issuing it.
The spatial framework includes Government Regulation No. 21 of 2021 concerning the Implementation of Spatial Planning and Minister of Marine Affairs and Fisheries Regulation No. 28 of 2021 concerning Marine Spatial Planning. The latter covers marine spatial planning, use, control and supervision. A project’s location must be checked against the applicable marine spatial plans and zoning arrangements; a licence for the gas activity does not, by itself, settle marine-space conformity.
The application may require technical information sufficient to identify the project footprint and its location, including coordinates and the relevant facility or pipeline configuration. The sponsor should evaluate marine-space requirements early enough to inform site selection, subsea routing, vessel positioning and project scheduling. If the project also includes onshore facilities, such as a receiving terminal, pipeline landfall or gas send-out infrastructure, separate land-based spatial conformity requirements may apply.
The regulatory treatment can differ depending on whether an installation is considered a fixed or permanent use of marine space, a vessel temporarily operating at sea, or part of a wider upstream activity. This classification should be resolved with the responsible authorities rather than inferred from the label “floating.”
5. Environmental Approval and Marine Impact Management
Floating LNG projects require environmental screening and approval under the applicable environmental framework. Law No. 32 of 2009 concerning Environmental Protection and Management, as amended by Law No. 6 of 2023, and Government Regulation No. 22 of 2021 concerning the Implementation of Environmental Protection and Management (GR 22/2021) govern environmental approvals and management obligations. GR 22/2021 remains in force.
Whether a project must prepare an Environmental Impact Assessment (Analisis Mengenai Dampak Lingkungan or AMDAL), an Environmental Management and Monitoring Effort (Upaya Pengelolaan Lingkungan Hidup dan Upaya Pemantauan Lingkungan Hidup or UKL-UPL), or another environmental document depends on the type, scale and location of the activities and the applicable screening criteria. Sponsors should assess the entire project scope, including offshore facilities, subsea pipelines, construction and installation works, onshore support facilities and associated vessel activities.
The environmental review should address marine and coastal impacts relevant to the project. These may include construction disturbance, discharges and emissions, waste management, marine biodiversity, underwater noise, spill prevention and response, and the environmental consequences of routine operations and decommissioning. Applicable technical approvals and environmental management commitments should be incorporated into the facility design and operating procedures.
The environmental approval process should be coordinated with the project’s marine spatial and business licensing workstreams. A change in location, capacity, technology or operating profile may require the project to reassess whether its existing environmental documents and approvals remain adequate.
6. Vessel, Terminal and Maritime Safety Requirements
The use of a floating unit brings maritime requirements alongside oil and gas regulation. Law No. 17 of 2008 concerning Shipping, as amended, and Government Regulation No. 31 of 2021 concerning the Implementation of the Shipping Sector regulate matters including shipping, vessels, navigation, port activities and maritime safety.
The applicable maritime requirements depend on the legal and operational character of the unit. If the FLNG or FSRU is operated as a vessel, the project should assess the requirements for vessel registration, flag, statutory certificates, seaworthiness, safety management and navigation. If the facility is treated as a stationary offshore installation or dedicated terminal, additional or different approvals may apply. The project should also determine whether LNG loading, ship-to-ship transfer, pilotage, port calls or the use of a special terminal require separate approvals or operational permissions.
Foreign-flagged vessel use and domestic maritime transport should be analysed separately. A foreign vessel’s presence at an offshore project does not automatically resolve whether a particular activity constitutes domestic sea transport, a specialised support operation or part of the offshore installation itself. The project’s transport legs, vessel functions and local operational arrangements should be reviewed against Indonesian shipping requirements before chartering decisions are finalised.
7. Gas Allocation, Domestic Use and LNG Export
An FLNG project’s commercial viability depends on having a legally supportable gas supply and sales plan. Gas allocation, utilisation and pricing are governed in part by Minister of Energy and Mineral Resources Regulation No. 6 of 2016 concerning the Allocation, Utilisation and Pricing of Natural Gas, as amended, including by Ministerial Regulation No. 9 of 2023. The applicable approvals should be checked against the project’s gas source, intended buyers, volumes and proposed domestic or export markets.
Domestic gas requirements and export sales must be considered together. A project should not assume that all planned production may be committed to export merely because an LNG sale and purchase agreement has been signed. The gas allocation, upstream approvals, applicable domestic requirements and export permissions must support the volumes and destinations contemplated by the sales arrangements.
As at 20 October 2026, export licensing requirements for oil and gas are also affected by Minister of Trade Regulation No. 5 of 2026, which amends the export policy and regulation framework under Minister of Trade Regulation No. 23 of 2023. For oil and gas exports, the 2026 changes simplify the export authorisation pathway, but exporters must still satisfy the applicable export approval and technical recommendation requirements. The Ministry of Energy and Mineral Resources identifies recommendations for exports of upstream oil and gas and recommendations for LNG exports in trading activities as distinct services.
Government Regulation No. 24 of 2026 concerning the Governance of Strategic Natural Resource Exports and its implementing trade regulations should also be screened when structuring export sales. The implementing 2026 trade regulations identified in the current official materials address coal, palm products and iron alloys. They should not be treated as automatically imposing the same special export mechanism on LNG without confirming whether the relevant commodity has been designated and brought within the applicable regime.
8. Measurement, LNG Quality and Custody Transfer
For a project involving upstream production and LNG sales, measurement and quality arrangements affect both regulatory reporting and commercial settlement. The project should define where gas or LNG custody transfers, how quantity is measured, which quality specifications apply, how measurement discrepancies are resolved, and how metering data is made available to the relevant parties and authorities.
A recent regulatory development is Minister of Energy and Mineral Resources Regulation No. 11 of 2026 concerning the Mandatory Application of the Indonesian National Standard for Quantity Assurance Systems in Upstream Oil and Gas Business Activities. It introduces a current standardisation requirement relevant to accountability and transparency in upstream quantity measurement. Sponsors and contractors should assess how this requirement applies to the project’s measurement systems and how it interacts with the metering and custody-transfer provisions in the LNG sales and operating contracts.
The technical and contractual design should be consistent across the upstream metering system, liquefaction process, LNG loading arrangements and buyer’s receiving terminal. Differences between measurement standards, calibration procedures or quality tolerances can create disputes over delivered quantities, off-spec LNG and payment.
9. Foreign Investment and Project Company Structure
Foreign investment should be considered at the level of each Indonesian entity and each activity it will conduct. Law No. 25 of 2007 concerning Investment, as amended, Presidential Regulation No. 10 of 2021 concerning Investment Business Fields, as amended by Presidential Regulation No. 49 of 2021, and Minister of Investment and Downstreaming/Head of the Investment Coordinating Board Regulation No. 5 of 2025 form part of the current investment and OSS framework.
The foreign investment analysis for an upstream PSC contractor is distinct from the analysis for a downstream processing, storage or LNG trading company. The project should confirm which entity will hold the PSC interest, own or charter the floating asset, apply for downstream business licences, provide technical services and sell LNG. Each entity’s permitted activities and investment conditions should be reviewed against the applicable business classification and licensing standards.
A foreign investor should not rely on a general assumption that LNG or offshore operations are either fully open or restricted. The applicable investment conditions depend on the activity and the business classification. A project-specific review should also consider corporate presence, foreign investment reporting, technical personnel, local content and procurement obligations that may apply under the relevant upstream and downstream arrangements.
10. Core Project Contracts and Risk Allocation
A floating LNG development typically depends on several contracts that must align with the regulatory approvals and the physical operating model. These commonly include the PSC, gas sales or gas allocation arrangements, a liquefaction tolling or processing agreement, a floating facility charter or lease, engineering, procurement, construction and installation contracts, operations and maintenance arrangements, LNG sale and purchase agreements, shipping contracts and terminal services agreements.
The contracts should clearly allocate responsibility for securing and maintaining each approval. They should also address which party bears the risk of delay caused by licensing, marine-space approval, environmental approval, vessel certification or export permissions. Where the facility is third-party owned, the project should specify who controls the vessel’s flag and classification, who holds the relevant operating approvals and what happens if the facility becomes unavailable or loses certification.
Commercial terms should address gas delivery and LNG output, quality and quantity specifications, commissioning and performance testing, operating availability, planned maintenance, fuel and boil-off gas, loading windows, destination flexibility, measurement, taxes, change in law, force majeure, decommissioning and removal. The project should also align the allocation of upstream gas and LNG sale volumes with approved development and utilisation plans.
If a project involves a dedicated facility that will remain offshore after the PSC or LNG service agreement ends, decommissioning, site clearance, asset transfer, removal security and environmental responsibilities should be settled at the outset. These obligations can materially affect the project’s lifecycle economics and the bankability of long-term contracts.
11. Practical Project Readiness Review
Before committing to a final investment decision, sponsors should test whether the project’s approvals, technical design and contracts describe the same operating model. In practice, this means confirming the upstream or downstream character of the liquefaction activity; identifying the relevant licence holders; validating the development plan and gas allocation; checking marine spatial and environmental approvals; and confirming vessel, terminal and export requirements.
The project should also confirm the status of gas supply and LNG offtake arrangements, the applicable export recommendation and approval pathway, and how the 2026 quantity-assurance standard will be implemented. Any gap between the commercial contracts and the regulatory structure can affect the project’s schedule, operating rights, financing conditions and ability to deliver LNG.
Conclusion
Indonesia does not provide one universal approval that authorises the development and operation of a floating LNG project. The applicable route depends on whether liquefaction is integrated into upstream production, conducted as a separately licensed downstream activity, or divided among multiple project companies and service providers.
For upstream-integrated projects, the PSC, approved development plan and SKK Migas oversight provide the core framework. Separate downstream activities may require business licences under Government Regulation 28/2025 and Minister of Energy and Mineral Resources Regulation 7/2026. Offshore siting and infrastructure may also require marine spatial conformity, environmental approval and maritime clearances. Gas allocation, domestic utilisation, export approvals and the new 2026 quantity-assurance standard should be integrated into the commercial and technical design.
The most reliable project structure is one in which each entity’s regulatory role is clear, the approval strategy matches the facility’s actual function, and the PSC, gas supply, tolling, charter, shipping and LNG sale contracts allocate risks consistently. Early coordination across these workstreams is essential to avoid treating a floating asset as though it were exempt from the rules governing the underlying gas activity, marine space or LNG export.