Industrial desalination projects in Indonesia require more than a business licence for water treatment. A project may need approval to use marine space for its intake and outfall,…

Industrial Desalination in Indonesia: Water Concessions, Coastal Approvals and Long-Term Supply Agreements

Industrial desalination projects in Indonesia require more than a business licence for water treatment. A project may need approval to use marine space for its intake and outfall, environmental approval for the plant and brine discharge, and depending on where the seawater is taken and how the product is used, a separate water-resource business permit. If the desalinated water will be supplied as drinking water for public needs, the rules governing Indonesia’s drinking water supply system also affect who may hold the relevant permit and how a private operator can participate.

The applicable framework has changed recently. Government Regulation No. 30 of 2024 concerning Water Resources Management (GR 30/2024) replaced Government Regulation No. 121 of 2015 on Water Resources Business Utilisation. The risk-based business licensing framework is now Government Regulation No. 28 of 2025 (GR 28/2025), which replaced Government Regulation No. 5 of 2021. For marine-space activities, Minister of Marine Affairs and Fisheries Regulation No. 28 of 2021 (KKP Regulation 28/2021) remains in force. A further recent change is Minister of Marine Affairs and Fisheries Regulation No. 13 of 2026 (KKP Regulation 13/2026), which governs the use of small islands and their surrounding waters and revoked the previous 2024 regulation on that subject.

1. The Project May Involve Different Water Rights and Approvals

A desalination project can involve three legally distinct activities:

  1. Using marine space for an intake, pipelines, outfall and related structures;
  2. Taking and processing water as a commercial activity; and
  3. Supplying water to an industrial customer, a drinking water supply system or the public.

The permits for these activities should not be treated as interchangeable. A marine-space approval does not, by itself, authorize a company to operate a water supply business. Conversely, a business licence for water treatment does not authorize construction of an intake or discharge structure in marine space.

The term “water concession” should also be used carefully. Under the water-resource framework, an authorization to use water for business is a public-law permission, not ownership of the water source. Its terms may include an approved location, volume or method of use. The project should identify which entity will hold each approval and whether that entity will also be the plant operator, the seller of water and the party responsible for environmental compliance.

2. Business Classification and Licensing

The applicable business classification depends on the project’s output and the entity’s role. The OSS system’s KBLI 2025 identifies KBLI 36001 – Drinking Water Treatment and Supply and KBLI 36002 – Raw Water Storage and Supply. The broader water activity classification covers salt removal from seawater where the principal output is freshwater.

There is an important qualification for seawater projects. Minister of Public Works Regulation No. 6 of 2025 concerning Business Activity and Product or Service Standards, Supervision and Sanctions in the Public Works Sector (PU Regulation 6/2025) describes the scope of KBLI 36002 as the storage and distribution of raw water from surface water other than seawater. Accordingly, a project producing and selling raw water from seawater should not assume that KBLI 36002 is the correct classification merely because its product is not potable. The project should confirm the appropriate KBLI and OSS licensing scope against its actual process, product specifications and customer use.

The construction contractor’s classification is a separate matter from the plant operator’s. For example, PU Regulation 6/2025 identifies a construction classification for civil works associated with water treatment infrastructure. The project company should therefore distinguish the operating business from contractors responsible for engineering, procurement and construction.

3. Water-Resource Business Permissions and Public Drinking Water

Law No. 17 of 2019 concerning Water Resources, as amended by Law No. 6 of 2023 (Water Resources Law), defines water to include seawater located on land. This makes the physical and legal location of the intake and water relevant: the marine-space approval for an offshore or coastal intake should be analysed separately from any water-resource permission applicable to seawater once it is brought onto land and used in a business. GR 30/2024 and Minister of Public Works and Housing Regulation No. 2 of 2024 concerning Procedures for Business Licensing for Water-Resource Use and Approval for Water-Resource Use provide part of the current water-resource framework. The applicable permission should be assessed against the project’s intake location, plant configuration and use of the product; it should not be assumed that every seawater intake triggers the same water-resource permit.

A more specific rule applies when the desalinated water is drinking water for people’s daily basic needs. The Water Resources Law provides that the business-use permission for water used as material to produce drinking water for those needs is granted to a state-owned enterprise, a regionally owned enterprise or a village-owned enterprise that operates a drinking water supply system. This creates a material structuring issue for a private or foreign investor planning to sell desalinated water directly into a municipal supply system.

Government Regulation No. 122 of 2015 concerning Drinking Water Supply Systems (GR 122/2015) remains in force. It permits cooperation between a state-owned or regionally owned drinking water system operator and a private business where the public operator cannot finance the required system. The regulation sets conditions for that cooperation, including that the relevant water-taking permission is held by the public operator and that the cooperation gives appropriate priority to low-income communities. The private party should therefore distinguish a bulk-water supply or project cooperation role from holding the public drinking water system’s underlying water-use permission.

The structure may differ where the water is produced for an industrial customer’s own process rather than supplied as drinking water for the public. Minister of Public Works and Housing Regulation No. 25/PRT/M/2016, which remains listed as in force, addresses drinking water systems operated by businesses to meet their own needs. It should be considered where the plant supplies a single industrial facility or a defined industrial operation rather than operating as a public utility.

4. Coastal and Marine-Space Approvals

KKP Regulation 28/2021 requires a Marine Spatial Utilisation Conformity Approval (Kesesuaian Kegiatan Pemanfaatan Ruang Laut or KKPRL) for fixed activities in coastal waters, territorial waters and/or jurisdictional waters. The regulation’s marine zoning framework expressly recognises seawater utilisation other than for energy, including water processing. It also covers marine space at the surface, in the water column and on the seabed. A desalination project’s intake, subsea or coastal pipelines, outfall and associated structures should therefore be assessed as marine-space uses, with the required KKPRL determined by the actual design and location.

The route and location assessment should be carried out before finalising engineering design or committing to construction. The project should check the applicable marine spatial plan and zoning, the location of other marine users and any restrictions associated with protected or sensitive areas. If the project is near a port, navigation route, fisheries area, coastal settlement or existing marine infrastructure, those interactions may affect the proposed intake or outfall design and the environmental assessment.

KKPRL is a spatial approval. It should not be described as a general concession over seawater or as a substitute for business licensing, environmental approval, land rights or any water-resource permission that applies to the project.

5. Projects on Small Islands: The 2026 Rule

Where a desalination plant, intake, pipeline or outfall is located on or around a small island, the project must also be screened under KKP Regulation 13/2026 concerning the Utilisation of Small Islands and Their Surrounding Waters. The regulation was promulgated on 14 September 2026 and is recorded as in force. It revoked KKP Regulation 10/2024, so the prior regulation should not be treated as the current framework for new project planning.

The small-island location may add a separate approval or recommendation process, including where foreign investment is involved. This assessment is distinct from the general foreign investment review and the marine-space approval. Project sponsors should verify whether the 2026 rule applies to the specific island, surrounding waters, investment structure and activity before relying on an earlier permit pathway or prior legal analysis.

6. Environmental Approval and Brine Discharge

Desalination projects should assess environmental approval for the plant and its marine works as a single integrated project. The screening should cover the intake, pretreatment, treatment process, chemical use, pipeline route, outfall and the expected volume and characteristics of the concentrate or brine.

Government Regulation No. 22 of 2021 concerning Environmental Protection and Management (GR 22/2021) remains the core environmental framework. Minister of Environment and Forestry Regulation No. 4 of 2021 provides the activity and scale criteria used to determine whether a project requires an Environmental Impact Assessment (Analisis Mengenai Dampak Lingkungan or AMDAL), an Environmental Management and Monitoring Effort (Upaya Pengelolaan Lingkungan Hidup dan Upaya Pemantauan Lingkungan Hidup or UKL-UPL), or an Environmental Management and Monitoring Undertaking (Surat Pernyataan Kesanggupan Pengelolaan dan Pemantauan Lingkungan Hidup or SPPL). The applicable instrument depends on the project’s characteristics, scale and location.

Where the project discharges wastewater or process effluent, Minister of Environment and Forestry Regulation No. 5 of 2021 on Technical Approvals and Operational Feasibility Certificates for Environmental Pollution Control (Permen LHK 5/2021) may require a Technical Approval and an Operational Feasibility Certificate, subject to the applicable requirements and any specific amendments. The regulation remains in force, although it has been amended in limited respects. The brine-discharge design should therefore be evaluated against the environmental approval, applicable marine water-quality standards and the project’s technical approval requirements; a general dilution assumption should not replace that assessment.

For projects supplying drinking water, the finished water must also meet the applicable health requirements. Minister of Health Regulation No. 2 of 2023 concerning the Implementing Regulations for Government Regulation No. 66 of 2014 on Environmental Health (Permenkes 2/2023) is the current health framework to assess for drinking water quality and monitoring.

  1. Non-Tax State Revenue for Seawater Utilisation

The marine-space and seawater-utilisation framework may also involve Non-Tax State Revenue (Penerimaan Negara Bukan Pajak or PNBP). Government Regulation No. 85 of 2021 sets types and tariffs of PNBP applicable to the Ministry of Marine Affairs and Fisheries, including for seawater utilisation other than energy. The procedures for imposing and paying relevant charges are addressed under Minister of Marine Affairs and Fisheries Regulation No. 39 of 2021, as amended, most recently for this purpose by Minister of Marine Affairs and Fisheries Regulation No. 30 of 2024.

The project should verify the applicable PNBP treatment and calculation against its approved activity and project data. The amount should not be assumed from a generic desalination benchmark, particularly where the project has multiple intake points, different operating volumes or a small-island location.

8. Foreign Investment and Project Company Structure

Foreign investment should be assessed under Presidential Regulation No. 10 of 2021 concerning Investment Business Fields, as amended by Presidential Regulation No. 49 of 2021, and the current risk-based licensing procedures under GR 28/2025 and Minister of Investment and Downstreaming/Head of the Investment Coordinating Board Regulation No. 5 of 2025. The applicable investment conditions depend on the precise business activity and current KBLI entry. A project should not infer that a particular ownership percentage is allowed r prohibited, merely because the plant uses seawater or supplies an industrial customer.

The investment analysis should be conducted separately from the public drinking-water permission analysis. A project company may be capable of holding an investment licence for its activity while still needing to structure public water supply through an eligible public operator. If the project site is on a small island, the additional approval regime under KKP Regulation 13/2026 should also be assessed.

For an industrial offtaker, the project structure may involve a project company owning and operating the plant and a customer purchasing water under a long-term agreement. For a public drinking water system, the structure may instead require cooperation with a state-owned or regionally owned operator, with the public operator retaining the relevant water-use permission and the private party participating under the applicable cooperation framework.

9. Structuring a Long-Term Water Supply Agreement

A long-term supply agreement should be aligned with the project’s permits, operating envelope and financing model. The contract should specify the product being supplied—such as raw water, process water or drinking water and make clear that the water-quality standard and intended end use match the relevant approvals.

The main commercial and regulatory provisions should address:

  • Quantity and allocation: contracted capacity, minimum and maximum volumes, ramp-up, scheduled outages and allocation during shortage or operating constraints.
  • Price and adjustment: base tariff, indexation, electricity and chemical-cost pass-throughs, taxes, PNBP where allocated to the supplier, and procedures for regulatory or cost changes.
  • Quality and testing: product specifications, sampling points, testing methods, monitoring frequency, rejection rights and remedies for off-specification water.
  • Delivery and measurement: delivery point, metering, pressure, losses, title and risk transfer, and responsibility for connecting pipelines and storage.
  • Permits and operating conditions: which party holds each business, water-resource, marine-space and environmental approval; reporting obligations; renewal responsibility; and the effect of a suspension, amendment or loss of a permit.
  • Brine and environmental compliance: responsibility for outfall operation, monitoring, incident response, environmental claims and any required changes to discharge conditions.
  • Continuity and default: force majeure, emergency supply, step-in rights, cure periods, termination rights, asset handover and coordination with lenders.

A take-or-pay or minimum-purchase obligation should be tested against permitted intake volumes, plant capacity, environmental limits and the customer’s actual demand. Likewise, the agreement should not assume that a regulatory approval automatically transfers if the project company is sold, reorganised or replaced. A change in the permit holder or the relevant project structure may require formal regulatory action.

Where a public authority or public drinking water operator is the buyer, the procurement and public-service framework should be assessed alongside the water-sector rules. If the project is structured as a Government and Business Entity Cooperation (Kerja Sama Pemerintah dengan Badan Usaha or KPBU), Presidential Regulation No. 38 of 2015 concerning Government Cooperation with Business Entities in Infrastructure Provision provides the general KPBU framework, with drinking water infrastructure included among the covered infrastructure sectors.

Conclusion

Industrial desalination in Indonesia is regulated through several connected but distinct regimes. The marine-space approval governs the physical use of coastal and marine areas; water-resource permissions may apply to relevant business uses of water, including seawater brought onto land; and separate licensing and supply-system rules apply to the operation and sale of water.

The distinction is especially important for projects supplying drinking water for public needs. The Water Resources Law reserves the relevant business-use permission for an eligible public drinking water system operator, while GR 122/2015 allows private participation through specified cooperation arrangements. For projects located on small islands, KKP Regulation 13/2026 is now the current additional framework and replaces the 2024 regulation.

A bankable desalination project should therefore settle the product classification, permit holder, intake and outfall approvals, environmental design, PNBP exposure and offtake structure before fixing the final tariff or financing model. The long-term supply agreement should reflect those regulatory dependencies rather than assume they can be resolved after construction.

This alert is part of a series examining regulatory developments affecting water infrastructure, marine projects, public utilities and foreign investment in Indonesia.