04 Nov 2026 · TAMA Insight
Offshore Wind Development in Indonesia: Marine Spatial Approvals, Project Licensing and Foreign Investment Considerations
Indonesia’s offshore wind sector sits at the intersection of electricity regulation, marine spatial planning, environmental approval and foreign investment rules. A project may require a viable wind resource…

Indonesia’s offshore wind sector sits at the intersection of electricity regulation, marine spatial planning, environmental approval and foreign investment rules. A project may require a viable wind resource and a route to market, but those factors alone do not give a developer the right to occupy a marine area, build generating facilities or connect to the grid.
As of 20 October 2026, the regulatory framework is spread across several laws and implementing regulations. The principal instruments include Law No. 30 of 2009 concerning Electricity, as amended by Law No. 6 of 2023 concerning the Stipulation of Government Regulation in Lieu of Law No. 2 of 2022 on Job Creation into Law (Electricity Law and Job Creation Law); Government Regulation No. 28 of 2025 concerning Risk-Based Business Licensing (GR 28/2025); Minister of Energy and Mineral Resources Regulation No. 7 of 2026 concerning Business Standards for Risk-Based Business Licensing in the Energy and Mineral Resources Sector (MEMR Regulation 7/2026); Government Regulation No. 21 of 2021 concerning Spatial Planning (GR 21/2021); and Minister of Marine Affairs and Fisheries Regulation No. 28 of 2021 concerning the Implementation of Marine Spatial Planning (KKP Regulation 28/2021).
The project must also be assessed against Government Regulation No. 22 of 2021 concerning the Implementation of Environmental Protection and Management (GR 22/2021), Presidential Regulation No. 112 of 2022 concerning the Acceleration of Renewable Energy Development for Electricity Supply (Presidential Regulation 112/2022), and the current investment and online licensing framework. These rules address different parts of a project. A marine spatial approval, electricity business licence, environmental approval and foreign-investment structure should therefore be assessed as separate but coordinated requirements.
1. Offshore Wind Projects Require More Than One Approval
There is no single offshore wind approval that replaces the other permits required for a project. A developer will generally need to establish:
- that the proposed wind farm and associated infrastructure are compatible with the applicable marine spatial plans;
- that the company holds the relevant business licences for electricity generation and any other activities it will carry out;
- that the project has obtained the environmental approval required for its scale and impacts;
- that the project has secured a feasible grid connection and electricity offtake structure; and
- that the project company’s foreign investment and corporate arrangements comply with the applicable investment rules.
The approval pathway depends on the project’s design. Relevant components may include the turbine array, foundations or anchors, offshore substations, export cables, cable landfall, onshore substations, construction areas and vessel activity. Each may raise separate spatial, environmental, land, safety or operational questions.
The current risk-based licensing framework is set out generally in GR 28/2025, with sector-specific business standards for energy activities addressed by MEMR Regulation 7/2026. Project teams should verify the licensing requirements against the business activities actually undertaken by the project company and the current requirements in the Online Single Submission (OSS) system.
2. Marine Spatial Approval and Site Selection
A developer should examine marine spatial compatibility before treating a proposed offshore area as available for project development.
The principal marine spatial instrument is the approval of marine spatial utilisation conformity, known as Kesesuaian Kegiatan Pemanfaatan Ruang Laut (KKPRL). GR 21/2021 and KKP Regulation 28/2021 form part of the framework for assessing whether a proposed marine activity is consistent with the applicable spatial plans and zoning arrangements.
For an offshore wind project, this assessment should cover the full project footprint, rather than the turbine coordinates alone. The review may need to take account of the turbine layout, safety zones, foundations, offshore substations, cable routes, construction and maintenance areas, and the route to shore. The relevant plans and uses to check may include shipping routes, fishing grounds, conservation areas, existing cables or pipelines, defence interests and other marine uses.
KKP has publicly described KKPRL as a basic approval for offshore wind projects and has reported issuing KKPRL approvals for wind-energy study plans in West Java and South Sulawesi. Those study-stage approvals demonstrate that marine spatial planning is relevant from early project development; they should not be treated as the complete set of approvals for construction or operation.
If a project area overlaps a marine conservation area, a protected coastal area or waters around a small island, the developer should separately assess the rules governing those locations. The applicable restrictions and approval pathway may differ from those for other marine areas. A project should not assume that a technically suitable wind resource can be developed until the relevant spatial plans and any location-specific controls have been checked.
3. Submarine Cable Routes and Grid Connection
The export cable is a core part of an offshore wind project’s marine footprint. It needs to be considered from the outset alongside the turbine area, because its route may cross existing marine infrastructure, shipping areas or other designated uses.
KKP Regulation No. 14 of 2021 concerning Submarine Pipeline and/or Cable Routes (KKP Decision 14/2021) remains listed as in force by KKP. KKP has also described coordination with PLN on offshore wind cable planning. Developers should therefore coordinate the cable corridor and grid connection with the relevant marine authorities and PLN, and confirm the approvals applicable to the particular route and connection design.
The project should also assess the terrestrial portion of the connection. Cable landfall, access roads, onshore substations and any transmission facilities may require separate spatial, environmental, land-use and construction approvals. A marine approval for an export cable does not, by itself, secure the rights needed to build or operate the onshore connection.
Grid connection should be treated as both a technical and a commercial workstream. The developer will need to understand the applicable system studies, connection requirements, network capacity, dispatch arrangements and any required connection or transmission agreements. A planned cable route should not be assumed to guarantee grid access or a power purchase commitment.
4. Electricity Business Licensing and Project Classification
A company generating electricity for supply to the public will generally need the relevant electricity business licence for public supply, commonly referred to as an Izin Usaha Penyediaan Tenaga Listrik untuk Kepentingan Umum (IUPTLU). A project designed to generate electricity for its own use may instead require an Izin Usaha Penyediaan Tenaga Listrik untuk Kepentingan Sendiri (IUPTLS), depending on the structure and applicable licensing rules.
These licences should be distinguished from the project company’s business identification number and other OSS approvals. The correct licensing path depends on the project’s intended activity, including whether it will sell electricity to PLN, supply another party, generate for its own use or undertake additional electricity activities such as transmission or distribution.
Under the Indonesian Standard Industrial Classification 2025 (Klasifikasi Baku Lapangan Usaha Indonesia or KBLI 2025), KBLI 35120 – Electricity Generation from Renewable Energy Sources covers generation from renewable sources, including onshore and offshore wind. Selecting the appropriate KBLI is a necessary part of business registration, but it does not itself grant an IUPTLU, marine approval or environmental approval.
The licensing assessment should also identify whether the company’s activity is limited to generation or includes other regulated functions. A project vehicle that owns a wind farm, a separate entity that operates the facility and a separate transmission or distribution entity may face different licensing requirements.
5. Renewable-Energy Procurement and the Power Purchase Agreement
Presidential Regulation 112/2022 establishes the framework for accelerating renewable energy development for electricity supply. The regulation is relevant to offshore wind as a renewable power source, but it does not guarantee a project’s inclusion in the power system or secure an offtake agreement.
A project selling electricity to PLN will need a commercially viable procurement route and a power purchase agreement (PPA) that meets the applicable requirements. Minister of Energy and Mineral Resources Regulation No. 5 of 2025 concerning Guidelines for Power Purchase Agreements from Power Plants Using Renewable Energy Sources (MEMR Regulation 5/2025) provides the current PPA guidance for renewable generation. The project’s prospects will also depend on system planning, procurement processes, grid capacity and the commercial terms that can be agreed.
Developers should therefore align site selection, marine approvals, environmental studies, grid studies and procurement strategy. A project may be spatially suitable but still face material uncertainty if the grid connection or offtake route is not established.
The National Energy Policy is now governed by Government Regulation No. 40 of 2025 concerning National Energy Policy (GR 40/2025), which replaced Government Regulation No. 79 of 2014. Offshore wind proposals should be assessed against current national energy policy and the prevailing electricity system plans, rather than relying on targets or assumptions drawn solely from the earlier framework.
6. Environmental Approval and Marine Impact Assessment
Offshore wind projects must obtain the environmental approval applicable to their scale and potential impacts under GR 22/2021. The environmental screening determines whether the project requires an Environmental Impact Assessment (Analisis Mengenai Dampak Lingkungan or AMDAL), an Environmental Management and Monitoring Efforts document (Upaya Pengelolaan Lingkungan Hidup dan Upaya Pemantauan Lingkungan Hidup or UKL-UPL), or another applicable instrument. The required instrument depends on the project characteristics and the applicable screening rules; the project should not assume that a single document type applies to every offshore wind development.
The assessment should address impacts relevant to the project’s location and design. These may include effects on marine habitats and protected species, fisheries and livelihoods, seabed disturbance from foundations and cable installation, construction noise, vessel traffic, navigation safety and the effects of operating infrastructure. The export cable route and landfall may raise additional issues, including sediment disturbance and impacts on coastal communities or habitats.
Environmental approval is not a substitute for marine spatial approval, electricity licensing or land and construction approvals. It is a separate requirement that should be integrated into the project schedule and design process. Changes to the layout, cable route, construction method or capacity may also require the developer to reassess its existing environmental documents and approvals.
7. Foreign Investment and Project Company Structure
Foreign investors should assess the proposed business activities against Presidential Regulation No. 10 of 2021 concerning Investment Business Fields, as amended by Presidential Regulation No. 49 of 2021 (Presidential Regulations 10/2021 and 49/2021). Those regulations establish the general framework for investment access and restrictions. The precise investment conditions should be verified against the applicable business classification and the activities the company will conduct.
A foreign investor commonly participates through an Indonesian foreign-investment limited liability company (Perseroan Terbatas Penanaman Modal Asing or PT PMA). The company’s incorporation, business classifications, investment information and risk-based licences should be aligned through OSS under GR 28/2025 and Minister of Investment and Downstreaming/Head of the Investment Coordinating Board Regulation No. 5 of 2025 concerning Guidelines and Procedures for Risk-Based Business Licensing and Investment Facilities through OSS (BKPM Regulation 5/2025).
The foreign ownership analysis should be conducted for each activity, not simply for the overall project. Electricity generation, electricity transmission, construction, engineering, vessel services and other project functions may have different business classifications and regulatory conditions. A project company’s foreign ownership position should not be inferred from the renewable-energy nature of the project alone.
Investors should also consider the project’s contractual structure. The project company may need to coordinate shareholder funding, development and construction contracts, equipment supply, vessel and cable-laying services, grid connection, the PPA, land arrangements and long-term operation and maintenance. Any use of separate affiliates or contractors should be reviewed to confirm which entity holds each licence and bears each regulatory obligation.
8. Electrical Safety, Construction and Operations
Electricity projects must comply with applicable electrical safety requirements throughout construction, commissioning and operation. Minister of Energy and Mineral Resources Regulation No. 10 of 2021 concerning Electrical Safety (MEMR Regulation 10/2021) remains part of the sector’s safety framework. The project should identify the required technical standards, competent personnel, inspections, certification and operating procedures for its generating and connection facilities.
The project must also assess construction approvals for its facilities. Offshore installations, offshore substations, cable landfalls and onshore substations may engage different construction, building, maritime or operational requirements. If the project involves construction or operation of port facilities, installation vessels, or other shipping-related activities, the applicable shipping and maritime requirements should be reviewed for those activities.
The commissioning plan should identify which approvals and technical certificates must be in place before the facility can begin commercial operation. Securing a PPA or completing construction does not remove the need to satisfy applicable safety and operating conditions.
9. Local Content and Procurement Planning
Domestic component and procurement requirements may affect equipment sourcing, construction contracts and project economics. Developers should assess the applicable domestic-product requirements for the project and its procurement structure, including Minister of Energy and Mineral Resources Regulation No. 11 of 2024 concerning the Use of Domestic Products in Electricity Infrastructure Development (MEMR Regulation 11/2024).
The applicable obligations should be checked against the relevant procurement, project and product requirements. Developers should avoid relying on a generic local-content percentage without confirming whether it applies to the particular equipment, procurement route and project stage.
Early assessment is useful because turbine components, foundations, cables, substations, installation vessels and technical services may involve different supply chains. Procurement planning should therefore be coordinated with project scheduling, financing conditions and any applicable local-content verification requirements.
10. Project Development Sequence and Key Risks
A practical development sequence is to screen the marine site and cable route first, then confirm the project company’s business activities and investment structure, and progress the spatial, environmental, electricity licensing, grid and procurement workstreams in parallel where possible.
Before committing to construction, the developer should confirm that it has:
- a marine spatial pathway covering the wind farm, cable corridor and related infrastructure;
- the applicable electricity business licences and OSS authorisations;
- environmental approval based on the project’s actual design and impacts;
- an agreed or credible grid connection and electricity offtake route;
- the corporate and foreign-investment structure required for its activities; and
- a plan for electrical safety, construction, commissioning and operations.
Several risks arise when these matters are treated as sequential formalities. A cable corridor may prove incompatible with other marine uses; an environmental assessment may require design changes; the company may hold a business classification that does not cover all of its intended activities; or the project may not have a confirmed route to market. These issues can affect financing, construction timing and the bankability of the PPA.
Conclusion
Offshore wind development in Indonesia requires coordinated marine, environmental, electricity, investment and project-structuring work. KKPRL and marine spatial compatibility are central to site development, while the electricity business licence, environmental approval, grid connection and PPA address separate regulatory and commercial requirements.
The current framework includes GR 28/2025 and MEMR Regulation 7/2026 for risk-based licensing, KKP Regulation 28/2021 for marine spatial planning, GR 22/2021 for environmental approvals, Presidential Regulation 112/2022 and MEMR Regulation 5/2025 for renewable electricity development and PPAs, and Presidential Regulations 10/2021 and 49/2021 for investment access. KBLI 35120 provides the relevant 2025 classification for renewable electricity generation, including offshore wind, but does not replace the project’s sectoral approvals.
For developers and investors, the key is to establish early that the proposed marine footprint, cable route, licensing structure, environmental assessment, grid connection and foreign-investment arrangements can work together. Because approvals depend on location, project design and intended electricity supply structure, each project should be assessed against its specific facts and the rules in force when its applications are submitted.
This alert is part of a series examining regulatory developments affecting energy, infrastructure, marine spatial planning and foreign investment in Indonesia. Please feel free to contact us should you wish to discuss these developments further.